| GC: | Marshall General Contracting | 
|---|---|
| Customer: | Fairmont Downtown Dallas | 
| Type: | Remodel | 
    The Fairmont Ballroom Remodel Project was scoped to replace the 15 large chandeliers located on the third floor ballroom.
    The old chandeliers measured approx. 9 feet in diameter and were replaced with a similar dimension fixture but the weight
    of the new fixtures greatly exceeded the weight of the old fixture. With the weights involved with this project given the
    use of large lifts and the fixtures on the 3rd floor of the building we had to have a structural engineer approve our
    lift plan and verify both the floor and ceiling could support the extra weight.
 Despite these challenges we 
    managed to finish this project on time with no impact to the rooms schedule.